We have executed numerous small and big projects in the past 14 years. Few important projects are listed below.
- Erection of 2 No. new 33/11kV Substation i.e., 33KV Outdoor SS at Sai Nagar & 33KV Outdoor SS at IDOC Anthaipally with Connected 33KV & 11KV Lines along with Construction of Control Room & other Civil Works on partial turnkey basis under T&D Improvement works in GHMC area of Master Plan Zone.
- Erection of 11 No. new 33/11kV Substations with connected 33KV & 11KV lines along with construction of control room & other civil works on partial turnkey basis under T&D Improvement works in Non-GHMC area of Medchal Zone
- Erection of 11 KV line to proposed General Industrial park at Sy.No.278 & 361 at IP-Siddapur (V) in operation section Kothur of Kothur(M), Rangareddy (Dist).
- Providing of 4th alternate source to 33/11kV Asifnagar SS from 132KV Seetarambagh SS by laying of 2.37KM of 3X400Sq.mm. XLPE UG Cable (Single Run) from the EHT SS and extending upt the now proposed 4-pole structure at near Gowtham Model School duly connecting to the existing 33KV line of 33KV Asifnagar-Mallepally UG Cable along with laying of 65 mtrs 3X400Sq.mm. XLPE UG Cable at SS as well as extension of 33KV bay, erection of 33KV VCB at 33/11kV Asifnagar SS for IN& OUT arrangement in Rethibowli Section of Mehdipatnam Sub-division of Mehdipatnam Division of Hyderabad Central Circle and the work executed by Master plan SD-VI Sub-Division of MP-1 Division of Hyderabad Master plan Circle under T& D Improvement Works (Summer Action Plan 2025)
- Providing of 2nd alternate source to 33/11KV IDPL SS from 132/33KV Balkampet EHT SS by erection of new 33KV feeder by laying of 2.2KM of 33KV 3X400Sq.mm. XLPE UG Cable (double run) and stringing of 2KM of 33KV 100Sq.mm. AAAC OH line over now proposed 32Nos. M+9 Towers & 23 Nos. 12.5mtr spun poles from the EHT SS to 33/11KV IDPL SS duly utilizing 2.3KM of existing 33KV Idle line along with erection of 33KV Breaker at the 33/11KV IDPL SS in Secunderabad Circle and the work will be executed by the Master Plan SD-V of Division-I in Masterplan Hyderabad Circle under T&D Improvement works (Summer Action Plan 2025.
- Erection of 33/11KV Sub Station with Connected 33KV & 11KV Lines at Arkathala Industrial Park, Nawabpet Mandal, Vikarabad District
- Erection of new 33/11kV Outdoor substation with connected 33KV and 11KV lines including civil works at Shambipur with 2x12.5 MVA PTRs in operation Bowrampet section of Jeedimetla sub-division in of Medchal circle.
- Shifting of 33KV, 11KV and LT Lines by erection of M+6 Towers & Shifting of DTR's due to "150feet Road widening works" from Bandamkomma to Ameenpur to M/s. HMDA COMMISSIONER, Bandamkommu (V), Patancheru Rural Section, Patancheru Sub-Division in Patancheru Division of Sangareddy Circle.
- Erection of new 33/11KV SS with connecting 33KV & 11KV lines along with civil works at KCR Nagar, 2BHK Narsapur village in Siddipet Mandal of Siddipet Town-I Section in Siddipet Town Division of Siddipet Circle
- Erection of 33/11KV indoor substation and laying underground cable 4Km, 33KV and 11KV UG cable 7Km at CM Camp office, Pragathi Bhavan, Hyderabad
- Laying of 33KV UG cable 3Km near Secretariat, Hyderabad
- 33/11KV Substation and Erection of testing, erection of new Sub-station along with connected lines and other civil works at SV College in Suryapet Town-II – Erection of M+9 Towers 20 No’s.
- 33/11KV Indoor Substation with necessary equipment and connected Lines with Control Room at Aditya Empress Towers near Shaikpet – Laying of 33KV UG Cable Upto 5KM, 11KV UG Cable upto 3KM.
- 33/11KV Indoor Substation along with control room, & other civil works at Sandhya Hotels near sunshine Hospital Raidurgam – Erection of M+9 Towers 2 No’s.
- Extension of Supply 1 No 3Ph 50KW Non Domestic loads duly erection of 11KV Dedicated Feeder New TSIIC Feeder and extension of layout complete HT/LT Networks at Ravalkole (V), Medchal Malakjgiri Dist – Erection of M+9 Towers 2 No’s.
- Shifting of 33KV, 11KV & LT Power Lines at Special Food Processing Zone, Budhakalan (V), Bellampally (M), Mancherial Dist – Erection of M+3 & M+9 Towers 48 No’s
- Shifting of 11KV lines & DTRs Passing through the Premises and along the approach road of proposed TSIIC Food Processing Zone, Sarvareddypally (V), Vangoor (M), Nagarkurnool Dist – Erection of M+6 Towers 4 No’s
- 33KV, 11KV LT lines & DTRs by dismantling of existing all poles, DTRs & M+6 Towers causing obstruction for road expansion by erecting new M+ Towers from Beeramguda mondey market to Kistareddypet - Erection of M+6 Towers 60 No’s
- Power Evacuation from new 132/33KV Patancheru EHT SS by erection of 1No. 33KV take off feeder mamely 33KV Kistareddypet feeder in Patancheru Division of Sangareddy Circle – Erection of M+9 Towers 9 No’s
- 33KV, 11KV, LT lines & 9Nos. DTRs from Beeramguda Kaman to Monday Market on request of M/s. HMDA – Erection of M+6 Towers 20 No’s
- Shifting of 33KV, 11KV, LT Lines & DTR Structures around the Uppal Junction (Uppal X Road) as the existing infra obstructing the Construction of Sky Walk at Uppal Junction of Habsiguda Circle – Erection of Towers 9 No’s
- Shifting of 33KV, 11KV & LT Lines by erection of M+6 Towers & Shifting of DTRs due to 150feet Road Widening works from Bandamkomma to Ameenpur to M/s HMDA Commissioner, Bandamkommu (V), Patancheru Rural Section – Erection to Towers 65 No’s
- Kanakamamidi 132KV to Chandanavalli Industrial Park – 33KV overhead 25Km line and erection of M+6 towers 440 No’s
- Erection of 33/11KV substation at Pet bashirabad, erection of towers 150 nos
- Erection of 33/11KV Substation at Janapriya Housing Society, Sainikpuri, erection of M+6 towers 86 nos